John Young Parkway Project

Overview

The bidding the process has been completed for the following phases of construction

  • The Early Work Contract was awarded to Wright's Excavating, Inc based in St Cloud, FL. The scope of work consisted of clearing of the bridge site, installing the preliminary MOT, erosion control measures, clearing for the pond and installing temporary fencing for the pond. The work began on December 23, 2008 and was completed on January 23, 2009. Bid Tabulation

 

  • Phase I, II and III of the John Young Parkway/Osceola Parkway Interchange and Carroll Street. The contractor that is being recommended to Osceola County by the Construction Manager is JR Davis Construction Co, Inc based in Kissimmee, FL Bid Tabulation. The work is scheduled to be complete in February 2011.

 

 

Overview

Contact Us

If you have any questions, comments or concerns about the John Young Parkway project, please contact us!

Powered by: WebSolvers, Inc.